Tender go/no-go checklist for small UK suppliers
A bid for a public contract can take days of work. Most of that is wasted if you find a knock-out requirement on the last evening, or if the contract was never a good fit. This checklist helps you decide in about ten minutes, using the notice and the tender documents, whether a tender is worth a bid.
How to use it
- Open the notice and download the tender pack. Have the specification, the evaluation criteria and the pricing schedule to hand.
- Answer the five knock-out questions. Any "no" means no-go until you can fix it.
- Score the six questions from 1 (poor) to 5 (strong). 18 out of 30 or more is a go.
- If it is a go, use the pre-submission list while you write.
The checklist works in this page: tick and score as you go, then use Print or save as PDF or Copy as text to keep a record. Nothing you enter leaves your browser.
What the scores mean in practice
Price competitiveness depends on the weighting. A tender scored on price alone suits a lean operator with low overheads; a tender that gives most marks to quality rewards strong method statements and references. In two cleaning tenders open in October 2026, one council window-cleaning contract was scored 100% on price, while a secondary-school contract gave 54% to written quality, 36% to price and 10% to a presentation. The same firm could rightly score these very differently.
Evidence is where first-time public-sector bidders usually lose marks. Private-sector references count if they are similar in size and type; say so plainly and give numbers.
Strategic value is a tie-breaker, not a reason to bid for something you cannot deliver. A lost bid that teaches you nothing is the most expensive kind.
A worked example
A council window-cleaning tender on Find a Tender (notice 091158-2026) was worth £300,000 excluding VAT across five area lots, scored on price only, with clarification questions due on 20 October 2026 and bids on 27 October 2026. For an imaginary six-person window-cleaning firm based nearby, the knock-outs were all yes apart from insurance levels, which were not in the notice and had to be checked in the pack. Scores of 5 for fit, 4 for geography, 3 for price, 4 for capacity, 3 for evidence and 4 for strategic value gave 23 out of 30: a go on the two nearest lots, with a third lot decided after costing. The scores are illustrative; the notice facts are from the published notice.
UK rules that change the answer
Price and TUPE risk. On cleaning and FM contracts, staff working on the contract usually transfer to the new contractor on their existing terms. The outgoing employer must hand over employee liability information at least 28 days before the transfer, but you need the staff data to price the bid, so check it is in the pack. See TUPE in cleaning tenders and how to price a cleaning tender.
Deadlines. For covered procurements under the Procurement Act 2023, the usual minimum tender period is 25 days with electronic submission and documents provided up front, but it can be as short as 10 days after a qualifying planned procurement notice. A short window for a complex contract is a reason to say no.
Registration. Buyers collect supplier information through Find a Tender, the central digital platform. Registering is free and done once; do it before the deadline week. See Procurement Act 2023 for small suppliers.
Below-threshold work. Below the thresholds a buyer may not advertise at all. When it does, contracts worth at least £12,000 (central government) or £30,000 (other authorities), including VAT, appear on Find a Tender. See Contracts Finder vs Find a Tender.
When to say no
- Any knock-out is still a no after the clarification deadline.
- The contract is a large share of your turnover and the payment profile would strain your cash flow.
- You would have to cut the specified hours or staff to reach a winning price.
- The requirement reads as if it were written around the incumbent, and you have no edge to offset that.
- Writing the bid would take people away from clients you already have.
Saying no to a poor-fit tender is a good result: it keeps your time for the next one.
Frequently asked questions
What is a bid/no-bid decision?
It is the decision, made before you write anything, on whether a tender is worth the time and cost of bidding. A good one checks the knock-outs first, then scores fit, price, capacity, evidence and risk.
How long should a go/no-go decision take?
This checklist takes about ten minutes once you have the tender pack. If the answer is borderline, spend another hour on the specification, pricing schedule and contract terms before you commit days to writing.
What score means we should bid?
In this checklist, all five knock-outs must be a yes and the six scores should total 18 out of 30 or more. Treat it as a prompt for judgement, not a formula.
Want a second opinion on one tender? I read the notice and the tender pack and send a one-page go/no-go check as a PDF by email, within one working day of receiving the pack. It is £95 fixed, and every check says what I did and did not read.
I am also offering a free founding check to the first few UK limited companies, LLPs or plcs in cleaning, facilities management or IT with a tender deadline at least 5 working days away.
Request a free founding check Order a £95 go/no-go check
Prefer to do it yourself first? Use the free 10-question should-we-bid check.
This checklist is a decision aid, not legal or financial advice. Every tender pack sets its own rules; where the pack and this checklist differ, follow the pack. Notice facts are from Find a Tender, published under the Open Government Licence v3.0.